Exhibitor Timeline: What to Order and When
A step-by-step timeline from booking your booth to returning rentals, with the show deadlines that affect technology orders.
The short answer
Start planning about three to six months before the show, beginning with the booth and the exhibitor manual and ending with move-out and equipment return. ConventionVendor.com suggests ordering booth technology as soon as your booth is confirmed and ideally four to six weeks before move-in. Deadlines vary by show, so replace each step below with the dates in your exhibitor manual.
Last reviewed October 15, 2026 by the ConventionVendor.com rental team.
Why the order of tasks matters
Show services depend on each other. You cannot size an electrical order until you know what will run in the booth, and you cannot finish a floor plan until you know where each screen and counter will sit.
Many show services also carry an advance-rate deadline, after which orders are often billed at standard rather than advance rates. Working backward from those dates keeps your technology plan from forcing a late or rushed order.
Every show sets its own schedule, even when two shows use the same convention center. Read the timings below as typical patterns and confirm each one in your exhibitor manual.
The exhibitor timeline at a glance
The table runs from booking through equipment return. Relative timings are common patterns rather than rules, and your show may move any of them earlier or later.
Fill in the actual date next to each task as soon as the exhibitor manual is released. Shared calendars work well when several people place orders for the same booth.
| When | Task | Notes |
|---|---|---|
| 3-6 months or more before the show | Book the booth and record its number and size | Popular shows often sell booths a year or more ahead |
| When the exhibitor manual is released | Read the manual and build a deadline calendar | Look for rules on power, internet, hotspots, booth height, and outside contractors |
| 6-10 weeks before move-in (varies) | Decide what equipment the booth needs | Screens, lead capture, charging, and kiosks drive the power and internet orders |
| As soon as the booth is confirmed, ideally 4-6 weeks before move-in | Place your booth technology rental order | Early orders have the widest choice during busy show weeks |
| Advance-rate deadline (often several weeks before move-in) | Order electrical, internet, furniture, and labor through the exhibitor kit | Later orders often move to standard rates |
| EAC deadline (often several weeks before move-in) | Register outside contractors who will work in your booth | Include any rental company that will deliver into or set up in the booth |
| Advance warehouse window (opens weeks ahead, closes days before move-in) | Ship freight to the general service contractor's warehouse | Late arrivals may be refused or handled at added cost |
| Final 1-2 weeks | Confirm deliveries, staff schedules, content files, and app logins | Share the booth number and move-in time with every vendor |
| Move-in | Set up the booth, connect equipment, and test everything | Your show assigns move-in times, sometimes by booth number |
| Show days | Staff the booth, charge devices nightly, and sync leads | Keep cases and spares stored where the show allows |
| Move-out | Pack equipment, file outbound shipping paperwork, and release freight | Many shows prohibit packing before the official close |
| After the show | Return rentals and follow up on leads | Use the prepaid return label or confirm the scheduled pickup |
Three to six months out: booth and exhibitor manual
Once the booth is booked, record its number, size, booth type, and the aisles it faces. Those details shape screen placement, outlet locations, and sight lines from the aisle.
When the exhibitor manual or service kit comes out, read it end to end rather than skimming the order forms. Rules on hotspots, booth height, hanging signs, and outside contractors often sit in sections far from the order links.
Copy every deadline into one calendar and assign an owner to each task. A single missed date, such as the EAC form, can complicate a delivery that would otherwise be simple.
Six to four weeks out: equipment, power, and internet
This is the busiest planning window. Settle on screens, tablets, kiosks, and charging, then use that list to size the electrical order and choose between a wired drop and venue Wi-Fi.
Place your rental order during the same window so the quote can confirm the delivery method and timing. ConventionVendor.com can align delivery with your show's move-in schedule and list what each device needs from your power order.
If an outside company will deliver or set up equipment in your booth, add it to the EAC form now. Many shows also want that company's certificate of insurance before move-in begins.
The final two weeks
The last two weeks are for confirming, not ordering. Late orders are sometimes possible, but they leave less choice and less time to test.
Use this window to make sure every delivery knows exactly where to go and who will meet it. A single printed contact sheet for the booth team helps on move-in day.
- Confirm freight tracking numbers and advance warehouse receipt
- Send the final content file for booth screens and test it on a matching display if possible
- Install lead retrieval logins and confirm each staffer can sign in
- Share the booth number, move-in date, and on-site contact with every vendor
- Print the key sections of the exhibitor manual, including service desk locations and move-out rules
Move-in, show days, and move-out
On move-in day, check that electrical and internet are live where your floor plan shows them before connecting equipment. Report a missing or misplaced outlet to the service desk right away, because fixes take longer as the hall fills.
During show days, charge every tablet overnight and sync leads at the end of each day. Secure small equipment after hours, since many crews work in the hall once the doors close.
At move-out, pack rentals in their original cases, keep cables with the devices they belong to, and follow the pickup or return instructions in your quote. Paperwork for outbound freight usually goes through the general service contractor's service desk.
Frequently asked questions
When does the exhibitor manual usually come out?
It varies, but many shows release the exhibitor manual or service kit a few months before the show. Check the exhibitor section of the show's website, or ask show management if nothing has arrived after you book.
What is an advance-rate deadline?
It is the date by which show services such as electrical, internet, and furniture must be ordered to receive the show's advance rates. Orders placed later are often billed at standard rates, so plan equipment before that date.
Can I order booth equipment after the show deadlines pass?
Rentals are often still possible, depending on availability, and show service providers usually take late or on-site orders as well. The trade-off is less choice and less time to test, so treat late ordering as a fallback.
Who should own the exhibitor timeline on our team?
One person should hold the calendar and confirm each task, even when several people place orders. That person becomes the single contact for show management, the general service contractor, and vendors.
Rentals for this
- Booth Tech Kits: Lead Capture iPads, Screens, and Charging
iPads for lead capture, a monitor on a stand, and a charging station, packed as one kit for your booth and delivered for move-in.
- Booth TVs, Monitors, and Video Walls
TVs and commercial displays on floor stands or truss mounts, and LCD video walls, sized so your message reads from the aisle.
- Show Wi-Fi, Hotspots, and Connectivity
Cellular hotspots, routers, and network gear for show offices, hotel suites, off-site events, and booths where the venue and show allow them.
Read next
- Trade Show Booth Technology Checklist by Booth Size
An item-by-item list of the screens, lead capture devices, charging, connectivity, cables, and spares a booth needs, sized for 10x10 through island booths.
- Shipping to a Convention Center: Advance Warehouse or Direct
How advance warehouse and direct-to-show-site shipping work, what material handling covers, and how to plan outbound freight at move-out.
- Exhibitor-Appointed Contractors (EAC): What Exhibitors Need to Know
What an exhibitor-appointed contractor is, why shows require registration, the typical forms and insurance, and how it applies to rental deliveries.
Want us to plan it with you?
Send the show, venue, booth size, and dates. We will recommend the equipment and quote the complete setup, delivered around your move-in.